MWA Contractors – Avg.15 engineers across all disciplines
Length of Project – 24 months
Blocks – 1 Tower
Installation – 444 Apartments
Height – 42 Storeys
Build Completed – Q1 2025

- Mains cold water (MCWS)
- Boosted cold water services (BCWS)
- Domestic hot water services (DHWS)
- Low temperature hot water services (LTHW)
- Above-ground drainage systems
- Full plumbing and sanitary fit-outs for bathrooms, kitchens and Cylinder Cupboards

The development is not only made up of 444 luxury new apartments. But also has amazing concierge and amenity facilities for its residents.
The key feature of this development being its game areas, gyms, and other luxury facilities throughout the building for all residents.

mwa role
We were commissioned to design, supply and install the complete plumbing and mechanical services package to this development.
Engaging with mechanical & public health specialist consultants to devise cost effective and efficient strategies across the above ground drainage and rainwater, Domestic water and LTHW systems.

Bankside at Colliers Yard is a topped-out residential skyscraper in the Greengate area of Salford, Greater Manchester.

MWADELIVERY
Working closely with the Architects and the clients design team, MWA helped select a high-end specification for all traditional bathrooms, en-suite bathrooms, penthouse, and amenity areas.
The project start date for the plumbing and mechanical works was March 2023, delivering the job across a 24-month period, handing over to the client on time in February 2025.