PROJECTNUMBERS
^

MWA Contractors – Avg.15 engineers across all disciplines

^

Length of Project – 24 months

^

Blocks – 1 Tower

^

Installation – 444 Apartments

^

Height – 42 Storeys

^

Build Completed – Q1 2025

MWA Leaf icon
SYSTEMSINSTALLED
  • Mains cold water (MCWS)
  • Boosted cold water services (BCWS)
  • Domestic hot water services (DHWS)
  • Low temperature hot water services (LTHW)
  • Above-ground drainage systems
  • Full plumbing and sanitary fit-outs for bathrooms, kitchens and Cylinder Cupboards
MWA Leaf icon
THESITE

Located within the colliers yards neighbourhood, Bankside is collection of one, two and three bedroom apartments and penthouses offering deluxe amenities.

Bankside Mechanical Plumbing in Manchester
MWA Leaf icon
CLIENTDEVELOPMENT

The development is not only made up of 444 luxury new apartments. But also has amazing concierge and amenity facilities for its residents.

The key feature of this development being its game areas, gyms, and other luxury facilities throughout the building for all residents.  

MWA Leaf icon
THEINSTRUCTION

mwa role

We were commissioned to design, supply and install the complete plumbing and mechanical services package to this development.

Engaging with mechanical & public health specialist consultants to devise cost effective and efficient strategies across the above ground drainage and rainwater, Domestic water and LTHW systems. 

Bankside Mechanical Plumbing in Manchester
MWA Leaf icon
KEYCONSIDERATIONS

Bankside at Colliers Yard is a topped-out residential skyscraper in the Greengate area of Salford, Greater Manchester.

MWA Leaf icon

MWADELIVERY

Working closely with the Architects and the clients design team, MWA helped select a high-end specification for all traditional bathrooms, en-suite bathrooms, penthouse, and amenity areas. 

The project start date for the plumbing and mechanical works was March 2023, delivering the job across a 24-month period, handing over to the client on time in February 2025.

MWA Leaf icon
COMPLETEDPROJECTS

new landmarks

MWA Eco Systems logo
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.